Archive for Thursday, September 4, 2008

Downtown construction update

September 4, 2008

¢ The water line is complete.

¢ The electrician will start installing electrical lines and setting light poles this week. Pending rain delays, the concrete for the sidewalks on the east side of Main Street will follow shortly and should be finished by the end of next week.

¢ The alley way between 7th and 8th streets east of Main Street now is accessible from the north and the south.

¢ The storm sewer is going well and Maple street is open to through traffic.

Construction meetings are at 9 a.m. every Tuesday at Eudora City Hall.